Ark. DOT tries out new contracting process for road projects

Me Photo Headshot
Updated May 11, 2018

Img 0078The Arkansas Department of Transportation is experimenting with the construction manager/general contractor (CMGC) form of contracting, which shifts liability and risks of cost overruns to the contractor.

The state legislature has given the department approval to apply the alternative to traditional bidding for three projects totaling no more than $200 million. The agency chose improving the Highway 10 and Interstate 430 interchange in Little Rock as its first project under the new pilot program.

Under the program, contractors submit requests for proposals to be involved in the design phase of the project. After the design phase, the contractor submits its cost estimate to build the project. If that cost is within 10 percent of the DOT’s cost estimate, the contractor wins the bid, according to the legislation. The contract sets a ceiling price that the contractor cannot exceed.

If the DOT and contractor’s cost estimates exceed a 10 percent difference, then the project goes through a competitive bidding process.

For the first project under the pilot program, the cost cannot exceed $70 million, according to the legislation. The Little Rock interchange project is estimated to cost $58 million.

In April, the DOT awarded the pre-construction work for the Little Rock interchange to Kiewit Infrastructure South of Fort Worth, Texas, according to ArkansasOnline.

According to the Federal Transit Administration, CMCG involves the contractor in the early stage to provide engineering and constructability reviews. The contractor is chosen for prior performance, safety record and other criteria.

For the DOT, the result is a one-stop procurement process. The contractor assumes responsibility for the construction project, as well as bidding and contracting for subcontractors.

The goal of the process is to “allocate work to the most capable, available firms, thereby controlling not just the overall price but also the work schedule, quality, safety management, and community impacts,” the FTA says.

Partner Insights
Information to advance your business from industry suppliers
Selecting the Correct Construction Tire Solution
Presented by Michelin North America
How High Fuel Prices hurt Your Business
Presented by EquipmentWatch
8 Crucial Elements of a Tire Safety Program
Presented by Michelin North America

The approach has some disadvantages. The owner loses some leverage over the price because of the lack of competitive bidders, according to FTA. It can also be difficult for less experienced contractors to have a chance to win the contract.