The Tennessee Department of Transportation has announced the official timeline on its upcoming $185 million James Robertson Parkway bridge project in Nashville.
The project, also identified as the State Route6/Victory Memorial Bridge, will lower the viaduct leading up to the bridge and reconstruct the parkway between Interstate Drive and South First Street, add signal intersections, upgrade utilities and expand traffic capacity. The bridge’s connection to the East Bank’s planned street grid will improve access to jobs, housing and Super Bowl LXIV in 2030, city officials say.
“Redesigning James Robertson Parkway is part of our citywide vision for infrastructure that makes it easier for all of us to move around,” said Nashville Mayor Freddie O’Connell. “It means a safer road, an efficient connection from East Nashville to downtown and a street grid for the East Bank where a giant concrete wall once stood.”
The project’s progressive design-build contract was awarded to Wright Brothers Civil Construction earlier this year. The contract, according to TDOT, allows for collaborative refinement throughout the project’s progress, provides flexibility and more accurate planning of phasing and scheduling, and allows for the overlapping of design and construction activities.

The full project is estimated to cost roughly $185 million, accoding to a Nashville Metro Council document.
TDOT expects crews to break ground in Spring 2027 and close the James Robertson Parkway/Victory Memorial Bridge to both vehicular and pedestrian traffic from next summer through Summer 2029. The project is expected to be completed in late 2029.
The viaduct, built in 1951, sees roughly 17,300 vehicles daily on average.