Tag: TBMs
Roadbuilding
VDOT to use tunnel boring machine for first time in Hampton Roads Bridge-Tunnel expansion
VDOT will use tunnel boring machine on Hampton Roads project. Check out how the tunnel boring machine will enhance the bridge-tunnel expansion today.
August 6, 2018
Roadbuilding
Bertha stopped after veering off course in home stretch of Seattle’s SR 99 tunnel
Seattle Tunnel Partners (STP) stopped Bertha, the largest tunnel boring machine in the world, on Feb. 28 to make adjustments before it continues on its last 1,000 feet of the 9,270 tunnel for SR 99. Officials report recent surveys indicate the machine is potential out of alignment by several inches. “STP is conducting additional survey […]
March 3, 2017
Roadbuilding
Bertha is nearly ready to start tunneling again
The massive tunnel-boring machine that’s been sidelined in Seattle for two years could be back to boring by New Year’s. The Washington State Department of Transportation announced that the Seattle Tunnel Partners had begun the final preparations before drilling gets started again with soil and sand being poured into the 120-foot-deep access pit on Sunday. Bertha […]
December 17, 2015
Roadbuilding
Bertha delayed again; won’t restart drilling until late December
The Seattle Tunnel Partners have once again delayed the restart of drilling for the State Route 99 tunnel, with Bertha not expected to start work again until Dec. 23. The Washington State Department of Transportation announced the revised schedule Thursday and said the tunnel most likely would not open until April 2018. That puts the project two years and four […]
October 26, 2015
Roadbuilding
Board rules WSDOT should have given contractor more warning about pipe struck by Big Bertha before stall
In regard to the drilling of the new State Route 99 tunnel below Seattle, the Washington State Department of Transportation (WSDOT) has few friends left. There remains disagreement between the department and the city of Seattle over who will pay to repair a water main damaged during the excavation of a repair pit for Big Bertha, […]
May 12, 2015
Roadbuilding
Did Seattle’s SR 99 tunnel really require Big Bertha? Indeco argues breakers are the answer
Tunnel boring machines such as Big Bertha, the 7,000-ton machine sidelined after a massive fail under the streets of Seattle, shouldn’t always be considered the most efficient option for creating big dig projects, says a new publication produced by Italian hammer manufacturer Indeco and released at the Intermat construction equipment trade show this week. […]
April 23, 2015
Roadbuilding
Water main damaged by Big Bertha repair excavation could cost WSDOT $4 million
Four months after crews temporarily stopped excavation on a repair pit for the world’s largest tunnel-boring machine due to ground sinkage, Seattle officials have now identified a major repair needed on a water main damaged by the sinking. Back in December, excavation stopped on the repair pit through which Big Bertha’s massive cutterhead was recently lifted as officials suspected groundwater pumping […]
April 14, 2015
Home
Big Bertha’s delays have pushed back the opening of the tunnel it’s digging by 20 months…so far
Seattle’s new State Route 99 tunnel is officially 20 months behind schedule, and it’s all Bertha’s fault. The Associated Press reports Washington State Department of Transportation officials are now saying that the new tunnel being dug beneath Seattle by Big Bertha, the largest tunnel-boring machine in the world, won’t open until August 2017. And they […]
December 24, 2014
Construction Equipment
Drilling delays a problem for tunnel-boring machine Big Bertha even as she slumbers below ground
Crews in Seattle are now expected to finish digging a 12-story pit to reach stalled tunnel-boring machine Big Bertha one month later than planned due to concrete pilings proving more difficult to drill through than expected, according to a report from the Seattle Times. Bertha, the world’s largest tunnel-boring machine went down from overheating in late January, […]
July 31, 2014
Construction Equipment
Repairs to Big Bertha will include 86 tons of steel reinforcement to tunnel-boring machine’s bearing, cutter drive
The largest tunnel-boring machine in the world needs a bit of reinforcement against the “wet and abrasive soils” deep below Seattle, according to a report from the Seattle Times. As such, repairs for Big Bertha will include the installation of 216 steel ribs and plates that will add 86 tons to the 7,000-ton machine, the paper […]
June 18, 2014
Construction Equipment
Camera gives a live view of construction on Big Bertha’s 12-story repair access pit
Just because Big Bertha is down for nearly a year, that doesn’t mean work around the world’s largest tunnel boring machine has come to a halt. And now thanks to a camera set up by the Washington State Department of Transportation, anyone can watch as that work progresses. After completing one-tenth of the 1.7-mile State Route 99 […]
May 13, 2014
Construction Equipment
PHOTOS: Amazing images of subway construction in the man-made caverns below New York City
[imagebrowser id=58] Back in June we showed you a handful of pictures from deep below New York City. And while they depicted ongoing construction on the city’s Second Avenue Subway, they looked like more something out of a sci-fi movie. The Second Avenue Subway is the first line to be built in NYC since 1932. […]
April 7, 2014