Penn. Turnpike to replace two bridges in less than two weeks
Call it a bridge-building blitz. The Pennsylvania Turnpike will replace two bridges within two weekends. The process known as accelerated bridge construction will save a year or more in construction time and cut costs, the Pennsylvania Turnpike Commission says. A similar process, though on a much larger scale, was used to replace the Interstate 85 […]
September 19, 2017
Roadbuilding
The I-85 collapse and the push of Accelerated Bridge Construction techniques
Recently, all  eyes were on Atlanta as the Georgia Department of Transportation (GDOT) and its contractor C.W. Matthews worked around the clock to reconstruct a fire-damaged Interstate 85 span. With a total of $3.1 million in incentives on the line to get the project completed by May 21st, GDOT’s handling of I-85 promises to be a case […]
June 5, 2017
Roadbuilding
I-85 bridge contractor C.W. Matthews donates portion of incentive money to Camp Hooray
I-85 bridge reconstruction contractor C.W. Matthews is donating $10,000 from the incentive money it received for completing the reconstruction of the downtown Atlanta bridge early to Extra Special People’s (ESP) Camp Hooray, the first summer camp built in the U.S. built specifically for special needs children. “C.W. Matthews is proud to be one of the […]
May 22, 2017
Roadbuilding
I-85 collapse update: Bridges over Piedmont Road to reopen by May 15
The reconstruction of the Interstate 85 bridges over Piedmont Road near Atlanta destroyed by fire at the end of March will be complete and open by May 15, a full month ahead of the original estimated completion date and 10 days ahead of a revised timeline issued last week. Georgia Department of Transportation (GDOT) Commissioner […]
May 11, 2017
Roadbuilding
I-85 Update: Georgia DOT says bridge will be rebuilt and open by May 25
Georgia Department of Transportation (GDOT) Commissioner Russell McMurry says the I-85 bridge over Piedmont Road reconstruction near Atlanta will be finished and open by May 25 in time for the annual heavy traffic weekend before Memorial Day. GDOT’s original estimated completion date had been June 15. The bridge was destroyed by fire at the end of […]
May 2, 2017
Roadbuilding
Georgia DOT taking advantage of I-85 closure with adjacent resurfacing
The Georgia Department of Transportation (GDOT) plans to resurface 6.6 miles of Interstate 85 near the current section of roadway closed for bridge reconstruction due to the March 30 collapse to “minimize additional disruption” to motorists in the area. GDOT says the resurfacing project, valued at $22.9 million, and extending from I-75/SR 401 to Clairmont Road, […]
April 21, 2017
Roadbuilding
I-85 collapse update: Atlanta commute times up, but travelers seeking alternate routes, transportation options
The Georgia Department of Transportation (GDOT) says an analysis of traffic patterns on Monday indicates metro Atlanta commuters are following the agency’s recommendations for alternative routes, public transit and telecommuting in the wake of the collapse and reconstruction of sections of Interstate 85. GDOT says there were “comparable volumes” in the area on most major […]
April 12, 2017
Roadbuilding
Replacing collapsed I-85 bridge in Atlanta will be a delicate, months-long process
Crews with the Georgia Department of Transportation (GDOT) began demolition this past weekend on the collapsed portion of Interstate 85 following a fire March 30 believed to have been set intentionally. Officials estimate the repairs, which will include 350 feet of interstate in both northbound and southbound directions, will take months to complete. The Federal […]
April 4, 2017